We carry out a planned programme of highway improvement works to maintain and improve Wrexham’s roads.
The carriageway, footway structural and surface treatment works are prioritised based upon annual condition survey data.
We have scheduled the following works to complete by the end of the 2024/25 financial year.
Community Highway Repairs
Road | Ward | Comments |
---|---|---|
Rhosddu Road - Egerton Street to King Street | Grosvenor | Completed - 26/10/2024 |
Crogen - Holyhead Road to 104 Crogen | Chirk North | Scheduled – 05/11/2024 |
Bluebell Lane outside Plas Acton Cemetery | Gwersyllt South | Completed |
Percy Road - Belgrave Road to Talbot Road | Erddig | Completed - 10/09/2024 |
Hill Street, Pentre Broughton - Clappers Lane to Post Office | Gwenfro | Completed |
Sutton Drive | Cartrefle | Completed |
Y Wern (Caia Park) | Queensway | To be confirmed |
Summerhill Road – Gwersyllt | Stansty | Completed – 16/09/2024 |
Cefn Road - Five Fords | Abenbury | Completed – 10/10/2024 |
Watts Dyke, Llay - Number 2 to Ffordd Gryffydd | Llay | Completed – 10/09/2024 |
Assembly Road - A525 to Manley Road | Coedpoeth | To be confirmed |
Chestnut Avenue - Overton Way to Derwent Crescent junction | Acton and Maesydre | To be confirmed |
Llewelyn Road, Tanyfron (near residential properties as far as Vron Farm) | Brymbo | To be confirmed |
Bryn Lane - Ridleywood junction to JCB | Holt | Completed – 11/10/2024 |
Ffordd Llanerch, Delfryn, Heol Mabon | Penycae | Completed – 06/09/2024 |
Talbot Road - Trefor Street to Salsbury Road | Erddig | Completed – 30/08/2024 |
Colliery Road, Chirk - Holyhead Road to Longfield | Chirk South | Completed |
Chapel Street - Gutter Hill to Clarke Street | Ponciau | Completed – 19/10/2024 |
Dolywern, Old Road Hyfrydle to Ty Issa | Dyffryn Ceiriog | To be confirmed |
Whitestones | Dyffryn Ceiriog | Completed – 07/09/2024 |
Watery Road - Bradley Road to Crossing | Brynffynnon | To be confirmed |
Strategic Roads
Road | Ward | Comments |
---|---|---|
B5069 - From junction of Willow Court to junction of Mount Fields | Bangor Is-y-coed | Completed |
A525 - From junction of Assembly Road to junction of Cemetery Road | Coedpoeth | Scheduled – 18/11/2024 |
A539 - From junction of Caer Efail to Chapel Street | Cefn East | To be confirmed |
A525 - Approach to Rags Hill | Bangor Is-y-coed | Scheduled – 30/10/2024 |
A528 - Queens Bridge | Overton and Maelor South | Completed – 20/09/2024 |
B5102- Llay Miners to junction with Pinfold Lane | Llay | To be confirmed |
B5069 - Approach to Worthenbury Bridge | Bangor Is-y-coed | To be confirmed |
B5099 - Croesfoel roundabout | Ponciau | Completed – 08/10/2024 |
B5426- Plas Coch roundabout to B&Q roundabout | Grosvenor | To be confirmed |
B5425 - From Rhosddu Industrial Estate to junction with Rhosrobin Road | Gwersyllt South | To be confirmed |
B5096 - King Street, Railway Road junction to Minshalls Croft | Cefn West | To be confirmed |
B5069 - Cae-Dyah Lane to Carreg y Ffranc | Overton and Maelor South | To be confirmed |
A5156 – Llan-y-Pwll link road, east bound from Old Wrexham Road to Borras Head | Borras Park | Completed – 28/09/2024 |
B5426 - Hill Street, Gardden Road to Queen Street junction | Pant and Johnstown | Completed |
A539 - Hanmer | Bronington and Hanmer | Completed – 29/09/2024 |
A495 - Bronington | Bronington and Hanmer | Completed |
A525- Gegin Road to Old Road | Minera | To be confirmed |
Vehicle Restraint Systems
These are road safety measures that contain and redirect vehicles such as safety barriers, parapets or terminals.
Road | Ward | Comments |
---|---|---|
High Street, Ruabon - removal of barrier | Ruabon | To be confirmed |
Mold Road by Alyn Waters | Gwersyllt | Completed – 30/04/2024 |
B road up to the crematorium - opposite the Rhostyllen football pitch leading to the overbridge | Esclusham | Completed – 04/10/2024 |
A483 - junction 7 Burton Bridge | Rossett | To be confirmed |
Heritage Way, Brymbo | Brymbo | To be confirmed |
Llan-y-Pwll Link Road | Borras Park | Completed – 11/07/2024 |
Structural
These are schemes which are classed as structural, e.g walls, fences, railings etc.
Road | Ward | Comments |
---|---|---|
Cook's New Bridge Weight Restriction 7.5T carries B5102 Rossett Road over River Alyn | Rossett | To be confirmed |
Old Bangor-on-Dee bridge that carries road into the village over The River Dee | Bangor Is-y-coed | To be confirmed |
Fadog Pont Grade 2 Listed carries C242 The Graig (Off B4500) near Pontfadog over River Ceiriog | Dyffryn Ceiriog | To be confirmed |
Herber Pont carries C243 Bronygarth Road over River Ceiriog | Dyffryn Ceiriog | To be confirmed |
Bangor-on-Dee by-pass bridge carries A525 Whitchurch Road over The River Dee | Bangor Is-y-coed | To be confirmed |
3 Coed y Felin retaining wall | Brymbo | To be confirmed |
Cefn Cut Footbridge carries a PRoW over dismantled railway track | Cefn Mawr | To be confirmed |
Pen y Gelli playing fields boundary wall, Coedpoeth | Coedpoeth | To be confirmed |
Cheshire View, Brymbo - Wall repair | Brymbo | To be confirmed |
Mill Lane, Penycae - Over run culvert | Penycae | To be confirmed |
Drainage
These are schemes on our drainage infrastructure that will be delivered via grant funding.
Road | Ward | Comments |
---|---|---|
Burton Road, Rossett - Drainage ditch at the road crossing | Rossett | Not yet completed |
Borras Retail Area - Soakaway and overflow | Borras Park | Completed |
Minera Community Phase 1 - Drainage scheme opposite Greengate Farm | Minera | To be confirmed |
Minera Community Phase 2 - B5426 Minera Hall Road - Road crossing near school | Minera | To be confirmed |
Graig Lane - Drainage overflow ditch | Bangor Is-y-coed | Not yet completed |
Maes Teg, Penycae - New drainage scheme | Penycae | Not yet completed |
Bowers Road, Acrefair - Trash screen | Cefn West | To be confirmed |
Francis Lane - Road crossing | Holt | Not yet completed |
Plas Madoc , Wynnstay Lane - New drainage scheme | Acrefair North | Not yet completed |
Stryt y Scweiar - Road erosion and ford reconstruction | Coedpoeth | Completed - 12/09/2024 |
Hollybush, Cefn Mawr - Blockage in footway | Cefn West | Not yet completed |
Chirk, Coronation Drive - Overflow connection | Chirk North | Not yet completed |
Marchwiel, Cross Lanes - Overflow pipe | Marchwiel | To be confirmed |
B5426 Mary's Gate, Eyton - Road crossing damaged pipe | Marchwiel | To be confirmed |
Ceiriog Valley, Bro Dewi - Trash screen repairs | Dyffryn Ceiriog | To be confirmed |
Ceiriog Valley, Mulberry Inn - Trash screen repairs | Dyffryn Ceiriog | To be confirmed |
Caia Park, Sutton Drive - Blockage in system | Cartrefle | Not yet completed |
Wrexham Industrial Estate, Oak Road - New headwall and drainage repair | Holt | Completed - 06/09/2024 |
Rhosddu, Balmoral Road - Drainage overflow repair | Stansty | Completed - 06/09/2024 |
Cefn Road - New drainage system | Rhosnesni | Not yet completed |
Straight Mile, Bangor-on-Dee - Road crossing | Bangor Is-y-coed | Not yet completed |
Footways
Road | Ward | Comments |
---|---|---|
Summerhill Road, Stansty - From junction 5 to Pendine Nursing Home | Gwersyllt West | Not yet completed |
Church Street, Gwersyllt | Gwersyllt West | To be confirmed |
Straight mile, Llay - From lights to Croes Howell Pub | Llay | To be confirmed |
Chester Street from Crown Buildings both sides to Seven Stars and Fusiliers | Acton and Maesydre | To be confirmed |
Rackery Lane, Llay - From Industrial Estate to border | Llay | To be confirmed |
A525 Bwlchgwyn – Kings Head to Monument | Minera | To be confirmed |
Chester Road, Rossett by Co-op store | Rossett | Completed |
Ffordd Llanerch | Penycae | To be confirmed |
Garner Road to Deva Way | Wynnstay | To be confirmed |
Solway Banks – Southsea playground area | Gwenfro | To be confirmed |
Hafod Wen | Pant and Johnstown | To be confirmed |
Castle Road, Coedpoeth left hand side towards Talwrn Road | Coedpoeth | To be confirmed |
Erw Lwyd | Rhosllanerchrugog | To be confirmed |
Ffordd Madoc | Borras Park | To be confirmed |
Wrexham Road, Rhostyllen | Ponciau | To be confirmed |
Fenant Road | Rhosllanerchrugog | Completed |
Station Road | Brymbo | Completed |
We aim to set out a definitive programme however it may be subject to change throughout the year. This could be due to budget adjustments or public utilities emergencies, for example.